Original Motion | Member Micah Miller Moved, Member Sarah Blissett seconded to approve the Original motion 'The Superintendent recommends adoption of the following resolution:
WHEREAS, the Board of Education has previously approved a Bid from below listed contractors for locations listed below; and
WHEREAS, the Architect for such project has recommended approval of a change order which complies with the applicable provisions of Chapters 122 and 38 of the Illinois Revised Statutes; and
WHEREAS, sufficient funds exist to provide payment for the additional requested change in this contract;
NOW THEREFORE BE IT RESOLVED that the Board of Education approves the following Change Order and directs the Superintendent to execute the necessary documents on behalf of the Board.
Location: Southeast High School
Change Order: #1
Amount: $19,673.35
Contractor: Johnco Construction
Scope of Work: Provide 3 station wash fountains in lieu of 2 station wash fountains. Work includes 8 restrooms.'. Upon a Roll-Call Vote being taken, the vote was: Aye: 7 Nay: 0. | The motion Carried 7 - 0 | | | Anthony Mares | Yes | Micah Miller | Yes | Sarah Blissett | Yes | Buffy Lael-Wolf | Yes | Erica Austin | Yes | Ken Gilmore | Yes | Debra Iams | Yes | |
|